Full-scope refurbishment direct to the client. 3,000 m² of Class B asbestos removal across the entire roof, then complete replacement with new zinc custom orb sheeting in 25 m runs, new gutters and internal cladding. QP coordinated every trade including removing and re-installing all the internal netting. Programmed at 14 weeks, finished in 8.
Full-scope refurbishment direct to the client. 3,000 m² of Class B asbestos removal across the entire roof, then complete replacement with new zinc custom orb sheeting in 25 m runs, new gutters and internal cladding. QP coordinated every trade including removing and re-installing all the internal netting. Programmed at 14 weeks, finished in 8.
Set-out, supply and install by QP Plumbing. In-house crew on site for the duration of the works. Coordinated with Direct to client throughout. Handover walk-through with the head contractor and signed-off defects list before we leave site.
Drawings, specifications and head-contractor reference available on request.